The most up-to-date information regarding road and lane closures will always be posted here. You can sign up to receive the latest email updates using the form in the sidebar.

We apologize for any inconvenience disruptions may cause. Motorists are advised to plan alternate routes and to drive according to conditions, slow down, stay alert and stay in control.

HWY 427

FINCH AVE

ALBION RD

STEELES AVE

HWY 407

HWY 7

ZENWAY BLVD

LANGSTAFF RD

RUTHERFORD RD

MAJOR MACKENZIE DR

HWY 50

 

TEMPORARY 


Hwy 427:

Northbound and Southbound Lanes on Hwy 427 (legally known as Regional Rd 99), Hwy 7 to Zenway Blvd 

Map depicting location of closure on Highway 427 between Zenway Boulevard and Highway 7 legally known as Regional Road 99Temporary road closure

  • Northbound and southbound lanes will be FULLY CLOSED, weeknights between 12:00 AM and 5:00 AM.
  • Single Lane closures on Regional Rd 99 between 7:00 PM and 6:00 AM may be in place instead of full closures.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • Detour routes will be in place.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Temporary lane restriction

  • Single Lane closures in northbound and southbound directions.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • Time: 10:00 AM to 3:00 PM on the scheduled dates.
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Highway 427, Finch Ave to Hwy 7

Temporary road closure, temporary lane restrictionMap depicting location go reduced lanes and temporary road closures on Highway 427 between Finch Avenue and Highway 7

  • Alternating single lane closures nightly on Hwy 427 9:00 PM to 6:00 AM Sunday to Thursday Nights / 11:00 PM to 9:00 AM Friday Nights / 12:00 AM to 11:00 AM Saturday Nights.
  • Ramp closures at Hwy 7, Finch Ave, and Hwy 407 10:00 PM to 5:00 AM Sunday to Thursday Nights / 10:00 PM to 8:00 AM Friday and Saturday Nights.
  • Dates: Tuesday April 23, 2019 to Saturday May 4, 2019.
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Highway 427 northbound between north of Rexdale Blvd and Hwy 407

Temporary road closure

  • Periodic full closures for up to 15 minutes in the northbound direction under the control of Ontario Provincial Police.
  • Dates: Thursday April 25, 2019.
  • Times: 1:00 AM to 4:00 AM on the scheduled date.
  • All work is weather permitting.

Finch Ave:

Finch Ave between Humberline Dr to Darcel Ave

Temporary lane restrictionsMap depicting temporary lane restrictions on Finch Avenue between Humberline Drive and Darcel Avenue

  • Single lane closures in eastbound and westbound directions.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • Time: 10:00 AM to 3:00 PM/ 7:00 PM to 6:00 AM on the scheduled dates.
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Albion Rd:

Albion Rd between Steinway Blvd and Codlin Cres Map depicting location of lane restrictions on Albion Road between Codlin Crescent and Steinway Boulevard

Temporary lane restrictions

  • Single lane closures in both eastbound and westbound directions.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • Time: 10:00 AM to 3:00 PM Monday to Saturday / 7:00 PM to 6:00 AM Sunday to Friday Nights, on the scheduled dates.
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Steeles Ave:

Steeles Ave W between Alcide St and Signal Hill AveMap depicting location of temporary lane restrictions on Steeles Avenue West between Signal Hill Avenue and Alcide Street

Temporary lane restrictions

  • Single lane closures in both eastbound and westbound directions.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • Time: 10:00 AM to 3:00 PM / 7:00 PM to 6:00 AM Sunday to Friday Nights, on the scheduled dates.
  • All work is weather permitting.
  • Work may not take place on all the dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Hwy 407:

No scheduled disruptions at this time.

Hwy 7:

Highway 7 between Vaughan Valley Blvd and and New Huntington Rd

Map depicting location of temporary lane restrictions on Highway 7 between Vaughan Valley Boulevard and New Huntington Road

Temporary long-term lane reductions (from 6 lanes to 4 lanes)

  • Dates: April 30, 2019 to July 2020.

 

Temporary lane restrictions

  • Lane closures in eastbound and westbound directions.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • Time: 10:00 AM to 3:00 PM (single lane closures)/ 7:00 PM to 6:00 AM (single lane closures) / 10:00 PM to 5:00 AM (2-lane closures).
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Zenway Blvd:

Zenway Blvd between Vaughan Valley Blvd and Huntington Rd 

Map depicting location of temporary lane restrictions on Zenway Boulevard between Vaughan Valley Boulevard and Huntington RoadTemporary lane restrictions

  • Single lane closures on Zenway Blvd from 10:00 PM to 5:00 AM.
  • Access to Hwy 427 Southbound will be closed; detour routes in place.
  • Eastbound access to Hwy 427 Southbound closed from 10:00 PM to 5:00 AM.
  • Westbound access to Hwy 427 Southbound closed from 12:00 AM to 5:00 AM.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • Time: 10:00 PM to 5:00 AM on the scheduled dates.
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

Zenway Blvd between New Enterprise Way and Rainbow Creek Dr 

Map depicting location of temporary long-term closures on Zenway Boulevard between New Enterprise Way and Rainbow Creek DriveTemporary long-term lane reductions (from 4 lanes to 2 lanes)

  • Dates: Sunday December 16, 2018 to Fall 2020.

 

Langstaff Rd:

Langstaff Rd between Huntington Rd and Hwy 27 

map showing location of temporary long-term lane restrictions on Langstaff Road between Highway 27 and Huntington RoadLong-term lane reductions (from 4 lanes to 2 lanes)

  • Dates: Thursday October 18, 2018 to Spring 2020.

 

Rutherford Rd:

Rutherford Rd between McGillivray Rd and Huntington Rd 

Map depicting location of temporary lane closures on Rutherford Road between McGillivray Road and Huntington Road

Temporary road closure

  • Short closures up to 5 minutes each performed under the control of the York Regional Police.
  • Date: Thursday April 25, 2019.
  • Time: 11:00 AM to 2:00 PM on the scheduled date.
  • All work is weather permitting.

Temporary lane restrictions

  • Single lane and road shoulder closures in eastbound and westbound directions.
  • Dates: Tuesday April 23 to Saturday May 4, 2019 .
  • Time: 10:00 AM to 3:00 PM Monday to Sundays / 7:00 PM to 6:00 AM Sunday to Friday Nights, right traffic lane closure.
  • 3:00 PM to 10:00 AM right shoulder closure on the scheduled dates.
  • No traffic lanes restricted overnight.
  • All work is weather permitting.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

 

Major Mackenzie Dr:

Major Mackenzie Dr between Hwy 50 and Huntington Road 

map depicting location of temporary lane restrictions on Major Mackenzie Drive between Highway 50 and Huntington Road

Temporary lane restrictions

  • Reduced to one lane, controlled by traffic flaggers.
  • Dates: Tuesday April 23 to Saturday May 4, 2019.
  • Time: 7:00 AM to 5:00 PM Monday to Sunday on the scheduled dates.
  • All work is weather permitting.
  • Work may not take place on all dates listed above.
  • *No closures will be implemented between the night of April 18 to the morning of April 23 for the long weekend.

 

Hwy 50:

No scheduled disruptions at this time.

PERMANENT 


Huntington Road between Major Mackenzie Drive and East’s Corners Boulevard

Permanent closure

Huntington Road will be permanently closed to through traffic between East’s Corners Boulevard and Major Mackenzie Drive. Please use alternate route. See Bulletin 04 for further information.

 

Please contact us with any questions or concerns.